Bridgwater Tidal Barrier Drop in Session 10th July 2017

On the 10th of July at Bridgwater Town Hall (2-7pm) the EA and SDC will reveal the final form of their scheme for the Bridgwater Tidal Barrier. Its construction will shape the town for the next two hundred years. It is planned to be commissioned in 2024 and designed to operate for 100 years. The operational date is a political one rather than climate driven and unlike most similar structures it will be located within the town rather than at the mouth of the river.  Mitigation of a similar fluvial flood event to 2014 is not part of the barrier’s function.

People have been focused on the barrier yet the river banks are the important bit; what happens to them will decide how radically our existing landscape will change and have far greater impact than a set of gates. The downstream river banks are being maintained in accordance with the FCERM Strategy (the national flood and coastal erosion risk management strategy for England).Individual polices are detailed in the local 2010 Shoreline Management Plan covering the next 20, 50 and 100 years.

For the Parrett those policies say that within the operational life of the barrier “The long term vision is for a more naturally functioning estuary, through construction of set-back defences under a policy of managed realignment.” Land is being returned to the tidal zone.

EA maps produced in 2010 show how that will be achieved at Pawlett Hams and Chilton Trinity. The recently released BTB secondary flood defence plan and residual flood risk maps show the long term policies are being put in place. Only the river banks close to Combwich and Chilton Trinity housing will continue to be raised. Farmland will ultimately be flooded and lost as the majority of the river banks will cease to be raised to match climate change. Steart Peninsula’s habitat will in due course be extended to Dunball and Chilton Trinity.

The present scheme means that the opportunity to increase the conveyance capacity of the Parrett capacity by moving a future replacement barrier downstream is lost. Taunton Deane and South Somerset may have to build fluvial storage on their land in the future. Opportunities for a cost effective bypass will be lost to the detriment of Bridgwater and West Somerset. As a naturally occurring event Somerset land owners will not receive compensation. Bridgwater will pay around £20m in lost land values towards the present scheme. A major economic impact on Somerset as a whole is just being ignored.

It is simply not true or credible that the BTB can somehow be divorced from the EA’s longer plan for the Parrett Estuary; a plan prepared in 2010 predating the 2014 flooding of the Somerset Levels.

The Bridgwater Tidal barrier in its present form passed its sell by date in 2014 when fluvial flooding moved from management on the Levels to flooding within our homes. Even today people still imagine that the Bridgwater Tidal Barrier is somehow part of the scheme to mitigate the 2014 flood, it could be but it isn’t. The Levels’ will still flood as they did in 2014 if we get similar weather conditions.

With little information in the public domain including the option studies that supported the original 7 location and the shorter list of 4 it is not unreasonable that this scheme has many questions of transparency.  it  is unacceptable that important and relevant information is not available to the public ahead of the final consultation on the 10th of July. That flood maps produced in September 2016 have only just been published giving people little time to understand the implications of what is planned.

If the FCERM Strategy and Parrett Estuary Flood Management Strategy are executed in their present form 1000’s of acres of agricultural land will be lost to food production. Is it morally right that the UK which cannot feed itself should export even more of its food production overseas and possibly deny food to others? This lack of responsibility on our part will no doubt be further compounded when our overseas aid budget has to be used to relieve a famine we as a nation knowingly or perhaps worse unknowingly contributed to.

To reach this situation there is a clear lack of leadership, vision, scrutiny and oversight by those organisations and people charged with delivering the plan and the infrastructure for Somerset. Neither SDC nor the SRA has any engineering or qualified staff able to lead on flooding and  has chosen not to bring in people that could. There is also a clear engineering  deficit in the delivery of Somerset’s flood defences.

People should go along to the consultation and ask

  1. Is turning the River Parrett back 500 to 1000 years and extending the Steart Peninsula wildlife habitat to Dunball whilst constraining economic development really what Bridgwater and wider Somerset need?
  2. Why wasn’t a barrier considered at Combwich and extending to Pawlett Hill that would protect the whole area. Arguments that we might impinge on the edge of the SSI is not an argument for not even looking at the possibility.
  3. Why does the barrier only do TIDAL and not  FLUVIAL (2014 rainfall) with equal importance?
  4. What is the extra cost of building a barrier with a bridge on it?

 

Steve Trowbridge CEng MICE MIStructE

 

 

Chilton Trinity and Pawlett Hams

The EA’s 2011 document Managing flood risk on the Severn Estuary provided the EA’s vision for Steart Peninsula  including what subsequently became the Steart Marshes salt marsh  scheme.

Pawlett Hams no longer protected after 2030

Under present plans six  years after the completion of the proposed Bridgwater Tidal Barrier Pawlett Hams will cease to be defended. That means that the river banks will no  longer be maintained and the process of handing more farmland back to the sea  will start again. The estuary will in time return to the state it was in more than 500 years ago before the levels were drained. According to the EA this will see 387 Ha or just under 1000 acres of farmland lost to food production and the local economy although only 47Ha  is actually required to make up for coastline squeeze.

The Parrett Estuary Flood Risk Management Strategy   (PEFRMS) is a document remarkable for its narrow  vision that is more interested in extending the habitat for birds  whilst  completely failing to understand or chooses to stay silent on the impact of saltwater on agricultural land. The only economic impact considered seems  to be tourism.

Parrett Flood Management Recommended Strategy

Section 2.1.6 (b) notes that

North Devon and Somerset Shoreline Management Plan (Hartland Point to Anchor Head), Halcrow, due 2010. We are concurring with their emerging policies.

As such much of the real detail  is provided in the EA’s Shoreline Management Plan rather than the overarching Parrett Estuary Flood Management Strategy which is a long term plan to let down the flood defences along the River Parrett allowing the sea up to the edge of Chilton Trinity and trading off land in Sedgemoor for economic development elsewhere around the Severn Estuary. It is a step back in time with individual communities afforded  long term term flood protection rather than comprehensive  flood defence.  The high level strategy  for the PEFRMS is provided below  following on is information from the shoreline management plan and recently available information for the preferential flooding of farmland as part of the Bridgwater Tidal Barrier Scheme.

Pawlett Hams Realignment is the complete loss of Pawlett Hams as can be seen from the key plan in the Parrett Estuary Flood Management Strategy  and noted in item c above.

Applicable Shoreline Management Plan delivery of the Strategy that includes the loss of 387 Hectares (1000 Acres of land) at Pawlett Hams is  reproduced below.

Parrett Estuary (Combwich to River Brue) Policies 7d38 to 7d42

Individual policies for various  sections of the River Parrett and adjacent land are listed below. 7d39 is  worth noting as it has the next major realignment of the flood defences after Pawlett Hams allowing the River Parrett to come up within 1000m of the village of Chilton Trinity.

Policies 7d38 to 7d42

Full copies of the EA policies can be found at

Steart Peninsula (Stolford to Combwich) 7d34 to 7d37

Parrett Estuary (Combwich to River Brue) 7d38 to 7d42

Timescales 

all documents refer to timescales and these are

  • Short Term (to 2025)
  • Medium Term (to 2055)
  • Long Term  (to 2105)

Chilton Trinity

South of the Parrett the EA ultimately proposed to let the marshes return to the very edge of Bridgwater  whilst Sedgemoor District Council  and the EA’s Bridgwater Barrier team have left a space at site 4 for a bridge that is on the way to a planned inter tidal area  and represents the expansion of the Steart Peninsula scheme  up to Bridgwater.

EA presentation Severn Estuary Forum 2017

Managed Realignment

the planned retreat of the existing flood defences

Policy 7d42 Flood defences from Dunball To the River Brue
Policy 7d39 Combwich to Bridgwater (Parrett west) managed realignment.

Those two policies when implemented will along with Steart Marshes and the Bristol Ports land transform the Parrett Estuary.  There will be no new link possible between West and East Somerset.

Future (long term) Inter tidal habitat – salt marsh and mud flats

Total agricultural  land lost to agricultural will be around 5000 acres. There is a certain irony that the EA policies will in reducing UK agricultural land export food production abroad and potentially increase famine oversees.

In the short term  the  proposed secondary flood defences  shown below are required because the EA will not keep  raising the banks above the present levels. sea level rise will continue and the frequency of seawater flooding will increase. The route of the secondary flood defence is not dissimilar to the future managed realignment above.

Secondary Flood Banks based on Bridgwater Tidal Barrier at Site 5

The gap in the flood defences at Walpole still left open for floodwater to flood the area as it previously did in the 80’s

After the planned completion of the Bridgwater Tidal Barrier  a 1:200 flood is expected by the designers to flood land to the north of Chilton Trinity with saltwater. The maps below represent some of the 50 maps prepared by the BTB designers to support the decision on location of the BTB barrier; the complete set of maps can be found on the SDC Strategic Flood Risk Assessment page.

The maps below show the impact of the river banks not being raised to match rising sea levels apart from  the protected communities. The end result is the preferential flooding of farmland with saltwater during certain tide and storm conditions as presented during the Severn Estuary Forum 2017   held in Bridgwater.

None of this information was presented during the two EA/SDC public consultations in 2016. 

2025 1:200 Flood Return

The map below shows one of  breach locations modelled. A breach can occur anywhere, the map does not say its saline (salt) flood waters escaping from the river. They are merely designed to provide an idea of the  likely consequence of it happening. The full pack of maps shows a number of breach locations and these are yet to published by Sedgemoor District Council.

River Bank fails at Dunball at land to the north of Chilton Trinity flooded

One of the maps produced by the designer showing the safety risks associated with their present scheme.

BRIDGWATER TIDAL BARRIER ; SITE 5; FLOOD HAZARD 1 :1000 YEAR FLOOD EVENT

 

Somerset’s 20 Year Flood Action Plan is not a Plan

Has anyone noticed  there actually isn’t really a plan for managing flooding in Somerset  be it Tidal or Fluvial. Lots of headlines and pictures of grandstanding councillors on river banks  but little substance.  Our particular collective flood Emperor has no clothes whilst the myth that somehow the Bridgwater Tidal Barrier (BTB) is part of the solution to the avoiding a repeat of the 2014 flood is allowed to persist. People imagine that things are being done and there is a big picture somewhere. There isnt.

The Somerset 20 Year Flood Action Plan is little more than a  maintenance list that should have been done and wasn’t; it is a complete misnomer. In three years since the 2014 flood  there is no  big plan looking forward  the next 200 years. There is no context that  explains where the value of all the money being spent is.

There is no excuse for such short sighted behaviour by our officials and elected representatives. At least the Somerset Rivers Authority (SRA) carried out an economic impact assessment of the 2014 flood which is more than the EA and Sedgemoor District Council (SDC) have done for the Bridgwater Tidal  Barrier.

The development of new ideas  seems to be more akin to those seeking alternative medicinal remedies; they seem to be ones that will turn the Levels into some theme park rather than look at something that can be delivered over the decades and centuries ahead. The  Managed  Retreat (Realignment) of our coastline is not a panacea to rising sea levels; it has its place but  needs to be challenged when there are viable options.  Giving the EA the excuse and licence to do little or nothing is not acceptable. Those involved with W&WT and the RSPB as consistent beneficiaries of these  EA policies and alongside Natural England makes an unholy alliance  that is no friend of Somerset’s people.

Plenty of councillors are sat on committees and they should be ensuring rigorous debate and the publishing of useful information rather than the almost complete lack of detail in the public domain. The private sector would not be allowed to get away with this lack of transparency or vision.

Since 2014 when it was rushed together for political expediency  little has been done or achieved whilst show case projects are not what they seem

Bridgwater Tidal Barrier

Despite knowing that  the rise in sea level  has no recognised end date Somerset has decided on a  100 year scheme. Our King Canute moment.

We are going to build a scheme that cannot be easily extended or modified knowing full well that something else will be needed in the future but we haven’t decided what. A scheme that  unlike any conventional tidal surge barrier  it is  actually to be in the town rather than down stream and at the mouth of the river. Bridgwater in  probably 10 rather than 100 years will have enveloped the proposed barrier site.  A solution with built in obsolescence that  can be bypassed on day one does not seem a great idea. Children born today may see the BTB torn down. Why would Bridgwater  buy it?”

Options such as closing the gap between Stockland Bristol  and Pawlett Hill less than 2 Km  ( 1.3 miles) long compared to around 15 km (10 miles) both banks from Combwich to the selected site in Bridgwater or 7.5 Km  if you allow Pawlett Hams to go the way of Steart Peninsula.

Two option studies paid for by the taxpayer and Combwich  not even considered as an option in either and the  backdoor flood route at Walpole still not acknowledged when the EA visits landowners. The credibility of the EA , its consultants and our oversight committees is very poor.

King Sedgemoor Drain Improvement

The King Sedgemoor Drain improvement is a Fluvial conveyance scheme that cannot reach its full potential because of the location of the tidal BTB upstream of Dunball Clyce. The EA in this matter described themselves in recent correspondence as the SRA’s sub contractor.

Silos

Flood schemes are kept in silos of fluvial and tidal rather than in developing a single holistic solution for Somerset. The EA and other organisations make it very difficult  to see the full picture. There is a serious lack of transparency,  accountability and independent review in the process.

By 2024 nearly £100m will have been spent and the Levels will still flood. The Bridgwater Tidal Barrier is seen and portrayed as a Bridgwater only scheme where as moving it downstream  of the KSD outfall would increase conveyance  under fluvial conditions benefiting the districts of Taunton Deane and South Somerset. The SRA is nowhere to be seen generating debate and  bringing together people to achieve a wider benefit to Somerset with state and local ratepayers money which was its reason to be created. The SRA’s one big opportunity missed. This is notwithstanding the missed economic opportunity for West Somerset

Transparency

There is more information in the public domain about EDF’s Hinkley Point C power station then there is about these schemes especially the Bridgwater Tidal Barrier. It appears  the EA did not want the Chilton Trinity  and Pawlett Hams landowners to be aware of  what would not be done to protect their land choosing to hide behind the rather opaque Parrett Estuary Flood Risk Management Strategy. Something noticeably low key to the point of invisibility  in the EA’s 2016 consultations at the Bridgwater Art’s Centre.

The reasons  that undertakings given by the EA and SDC in Protecting Bridgwater and the Somerset Levels & Moors from Tidal Flooding-Flood Risk Management Review -November 2014 were never followed through and just quietly dropped has never been explained.

No imagination  and no vision for our children’s future

With a blank sheet of paper and little or no restrictions on what we might do to protect the South Somerset Levels including areas of Sedgemoor, Taunton Deane and  South Somerset there is still a blank piece of paper. Rarely has such an opportunity been squandered.

There is nothing that explains what happens to the Tidal Surge Barrier when we cannot raise the banks any longer which in reality we cant now and Pawlett Hams and Chilton Trinity have become mudflats/ salt marsh  and the cost of building downstream  prohibitive.

What we do have is lots of committees

Wessex Regional Flood and Coastal Committee (RFCC)

Board of the Somerset Rivers Authority (SRA)

SRA Joint Scrutiny Panel

Somerset Drainage Board Consortium (IDB)

Its interesting to note how many people sit  on more than one of these committees. These committees  have people with no engineering knowledge or experience apart from the EA & IDB and all EA’s donkey work is done by US and Canadian third party consultants with no attachment to the area. The EA’s contribution to Somerset is questionable now as they have been reduced to little more than a middle man.

we must also not forget the groups

  • SRA  Management Group
  • SRA Technical Group
  • Bristol Channel Strategic Coastal Group
  • South West Coastal Group
  • Southern Coastal Group

It really is time that Somerset had  a suitable organisation capable of bringing a long term vision to secure the future of Somerset. Whilst attendance at committees is so lucrative  nothing is going to get done .  The EA is not a delivery based organisation and needs to be changed or replaced.  The SRA has no structure or suitable people able to develop and execute the vision and solution we need. The system  we have is clearly not fit for purpose.

The situation for Somerset, the rest of the West Country and no doubt other regions of the UK is that they need their own independent Engineers with local knowledge. Engineers able  to provide continuity  in advice to the committees and oversee the EA and IDB and other agencies.

We cannot afford

  • that each agency (EA, Highways, Rail) continues to builds its own thing, we need to combine flood defence with other infrastructure works.
  • that strategic flood decisions can be left to seconded senior local authority officers  with little or no knowledge of the subject.
  • the lack of an independent peer review process.
  • The lack of transparency – there is nothing published on the BTB website that tells you why.  There is little value value in an undated progress report  that can be found there  that does not measure progress. 
  • all these organisations whose main purpose seems to be to invite people from other groups to attend their meetings at our expense.

WE NEED A PLAN and we need to end the Flooding Golden Goose. 

on the 14th of July 2017  a meeting of the Scrutiny Committee  will take place in Taunton . It is open to the public. 

http://www.somersetriversauthority.org.uk/about-us/sra-scrutiny-meetings-and-papers/